© 2024 KVPR | Valley Public Radio - White Ash Broadcasting, Inc. :: 89.3 Fresno / 89.1 Bakersfield
89.3 Fresno | 89.1 Bakersfield
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

Friant-Kern Canal Slows By 60 Percent, Subsidence To Blame

Friant Water Authority

A section of the the Friant-Kern Canal in Tulare County is sinking so much that it's lost about 60 percent of its flow.

Doug DeFlitch with the Friant Water Authority says the canal that helps irrigate a million acres of farmland has sunk two to three feet in some places over about a 25 mile area. The original design capacity in the area is about 4,000 cubic feet per second and he says it’s dropped to 1,600 cfs. 

"Underneath the bridge at Avenue 96 the water was impounding on the side of the bridge where historically it would be able to go underneath the bridge." - Doug DeFlitch, Friant Water Authority

The 152-mile canal from Millerton Lake to Kern County was built in the 1940s. It also supplies water to places like Lindsey, Orange Cove and Terra Bella.

DeFlitch blames the subsidence on five years of drought, the over-pumping of groundwater and the geology of the region. As water is pumped out of the ground the clay the area is made up of collapses causing subsidence.

"One of the ways we discovered the subsidence was we were delivering some floods waters in January down the Friant-Kern Canal and underneath the bridge at Avenue 96 the water was impounding on the side of the bridge where historically it would be able to go underneath the bridge,” DeFlitch says.

Subsidence along the waterway is affecting how gravity forces water down the canal — it was designed with a slope of six inches per mile to ensure flow. He says his team has reduced the amount of water in the canal to make up for the difference.

He says the lack of flow is limiting groundwater recharge and access to water for farms and towns that draw from the canal. “Their capacity is limited, but some of the water districts have been able to mitigate those impacts by switching to their Kern River supplies or other local supplies,” DeFlitch says.

The sinking starts around the Tule River and only worsens as the water flows southward. He says the deepest sinking is near the community of Terra Bella.

Credit NASA JPL

The problem mirrors subsidence detected in a 60 mile area around the town of Corcoran. That area has dropped by at least two feet according to a satellite mapping project by NASA from 2016.

“Subsidence by really no surprise is continuing there, but it’s actually got a lot faster during the drought period,” says Tom Farr with NASA’s Jet Propulsion Laboratory. “In those areas they’re just more susceptible. They have certain kinds of layers of fine grain material that are the type that compact and they pump too much.”

"This is going to be a big a big project and a big issue with all the potential critical challenges that farmers are facing right now." - Doug DeFlitch, Friant Water Authority

To fix the flow problems DeFlitch says the entirety of the canal needs to be adjusted to make up for the subsidence, which will cost around $400 million. But because of the high price tag he says his team is focusing first on fixing the area most severely impacted. Even though only preliminary design work has been done, he says to raise the canal by three feet will cost tens of millions of dollars and about three to five years to complete.

“This is going to be a big project and a big issue with all the potential critical challenges that farmers are facing right now [groundwater over pumping rules, etc.],” DeFlitch says. “This is going to be an important one to get fixed.”

Similar repairs were made during a time of drought in the 1970's. DeFlitch says in some places the banks were raised by six feet.

“After the 1977 drought the Bureau of Reclamation came in and did a capacity correction project — it cost millions of dollars,” DeFlitch says. “They installed several pumping plants for turnout in the area. They raised the canal linker, raised several bridges. They actually lifted the bridges up and changed the approaches to the bridges.”

DeFlitch says the plan to fix the problem may include erecting new bridges, building a pumping plant to increase the pressure of water flowing down the canal, raising banks or even re-routing the canal in some places. But he adds that all depends on funding.  He says the earliest anything will be done is sometime in 2019.

“There’s been a significant change in water supply use, crop patterns and demand patterns across the Valley since 1951,” says DeFlitch. “There’s a real need to look at the canal because of that.”

Ezra David Romero is an award-winning radio reporter and producer. His stories have run on Morning Edition, Morning Edition Saturday, Morning Edition Sunday, All Things Considered, Here & Now, The Salt, Latino USA, KQED, KALW, Harvest Public Radio, etc.
Related Content